Q How
long does the tendering and construction phase take?
The tendering process takes 4-6 weeks. Project commencement
relies on the contractor's commitments and the ordering time on
materials. Many paving materials can take a minimum of 6 weeks before
delivery and contractors require at least this much notice before
they are able to attend the site. It is not unusual for the commencement
of a project to be determined by the application and acquisition
of engineering specifications or Council approval for such features
as swimming pools. Pool construction can take up to 8 weeks. Landscape
construction on an average suburban garden can take at least as
long.